The Village of Princeville will be doing
curb and gutter replacement, sidewalk replacement
and pavement resurfacing on South Cottage Grove Ave.
The project should be complete by the first week of October
depending on weather. R.A. Cullinan is contracted to do the work.
The project will be on:
Cottage Grove from Rt. 90(West Spring St.) south to Blanchard St. When work begins, the section of road will be blocked off for thru traffic. There will be a detour going west out of town to Duncan Road,
then south on Duncan Road to Laura Road, then back east on
Laura Road to Princeville/Jubilee Road.
Residents that live on Cottage Grove will be allowed to travel to their homes most of the time, however, there will be some times that road will be completely shut down. When it is shut down, residents will have to park on side streets or access their property from the alley if available. Mail should be delivered to the properties most days. If there are times they cannot, the contractor will make provisions. All traffic except large truck traffic can still access Cottage Grove/Princeville Jubilee
by way of Douglas St.
Road work is expected to be
completed by Friday, September 28.
(barring any unexpected delays
or weather issues)
If there are any questions, please contact,
Superintendent of Public Works, Chad Gardner, 309-678-4151.
|
No comments:
Post a Comment